AI Solar Ltd and UK Sol came together to deliver a full clean energy install at Farnham Common Sports Club — and the club is now saving over 50% on it's electricity costs.
LOCATION: Farnham Common Sports Club
PROPERTY TYPE: Commercial Community building
SYSTEM SIZE: 21kW
PANELS: UK SOL 435W tigo optimised x 49
INVERTER: Sigenstor 25kW Hybrid Inverter
BATTERY: Sigenstor 10.0 (9.04kWh usable)
ANNUAL GENERATION: 16,700kWh (18,000 in 2026)
ANNUAL SAVING: over 50% on their bill
PAYBACK PERIOD: 4.5 years
CO₂ SAVED PER YEAR: 8.9 tonnes
INSTALL DURATION: 2 weeks
COMPLETED: Jan 2026
The customer was facing rising electricity costs eating into the ability to operate the community sports club.
Being a Sports Club there is also the ever present danger of cricket balls as well as footballs.
A thorough assessment was carried out on the existing structure, which was found to be unsuitable for mounting the Solar PV. Subsequently, it was decided to fit the PV onto the newer section of the building which could take the weight of the panels. Due to the layout of the building we needed to position the inverter and battery pack a significant distance from the main incoming supply which placed constraints on monitoring ability. We also had to specifically select compatible circuit protection for the building. Our team has been providing regular checks to ensure the system is operating at maximum efficiency. We also offer repairs if needed.
The Team had to battle the seriously wet winter, work around existing bookings and navigate the rabbits warren of roof structure that was hosted underneath the industrial over clad roof.
Significant reduction of bills going into the thousands of pounds for the Sports Club.